Why Mass. Lags On Patrick’s Wind Power Goal

WBUR  Five years ago, Gov. Deval Patrick set an ambitious goal: He declared that by 2020 the state should develop enough wind-generated electricity to power 800,000 homes. Patrick said a quarter of that wind power should come from turbines located on Massachusetts land.

But with half the time gone, we’re still far from reaching the governor’s goal for wind power.

After Delay, Hoosac’s Built

Dec. 3, 2012, was an overcast day in Berkshire County, but that didn’t dampen Patrick’s enthusiasm. He went to the rural northwest corner of Massachusetts to mark the near-completion of the Hoosac Wind Power Project, the largest in the state — 19 huge turbines built on two mountain ridges in the towns of Monroe and Florida.

“You don’t want them everywhere, but when you think about what they’re doing in terms of a clean, renewable and reliable source of electricity, it adds to the beauty,” Patrick said. “I think they’re quite elegant.”

But when it comes to wind power, beauty is in the eye — and ear — of the beholder. Opponents sued Hoosac, calling the 330-foot-tall turbines eyesores, loud and unhealthy. The lawsuits doubled the permitting time and the initial cost estimates.

After eight years of delay, the state’s highest court settled the matter. The $90 million Hoosac wind farm was built. (Full Article)